In project scheduling, what is the dependency type where one task must finish before the next can start?

Prepare for the PMT4810 Preventive Medicine Practitioner Certification Exam. Study with multiple choice questions and detailed explanations. Get ready for your certification!

Multiple Choice

In project scheduling, what is the dependency type where one task must finish before the next can start?

Explanation:
Finish-to-start is the way to ensure proper sequencing: the next task cannot begin until the previous one finishes. This is the standard dependency used in most project schedules, forming the basic link in the network that defines the order of activities and allows calculation of early/late start and finish times and the critical path. For example, you must complete the design before you can start prototyping. A lag would introduce a delay after the first task’s finish before the second starts, which is a modification of the timing, not the fundamental relationship type. The other terms refer to actions or documents outside the sequencing of tasks.

Finish-to-start is the way to ensure proper sequencing: the next task cannot begin until the previous one finishes. This is the standard dependency used in most project schedules, forming the basic link in the network that defines the order of activities and allows calculation of early/late start and finish times and the critical path. For example, you must complete the design before you can start prototyping. A lag would introduce a delay after the first task’s finish before the second starts, which is a modification of the timing, not the fundamental relationship type. The other terms refer to actions or documents outside the sequencing of tasks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy